Project Timeline
PRE-APPLICATION CONSULTATION AND COMMUNICATIONS
2 0 2 3
NOVEMBER:
Virtual Community Consultation Meeting Hosted by The City of Toronto - Nov 23, 2023
JUNE:
Filing of Ontario Land Tribunal Appeal – June 23, 2023
Update meeting with Interest Groups – June 12, 2023
Rezoning / Official Plan Amendment Application Resubmission date - June 9, 2023
JANUARY:
· Community Consultation Meeting - January 11, 2023 – Hosted by the City of Toronto
2 0 2 2
DECEMBER:
Meeting with The Village of Islington Business Improvement Association (BIA)
Meeting with 9 Burnhamthorpe Cres. Condo Corporation
Meeting with the Etobicoke Historical Society
NOVEMBER:
Meeting with The United Islington Church
APRIL:
Launch of Project Website
Application Submission
-Rezoning, Official Plan Amendment and Site Plan Control
Meetings with the Office of Councillor Grimes
-Date: April 6, 2022
Purpose: To discuss the vision of the site, review plans and receive feedback
2 0 2 1
OCTOBER:
Date: October 28, 2021
Purpose: To discuss the vision of the site, review plans and receive feedback
City Planning Staff (PAC):
Date: October 25, 2021
Purpose: To introduce the project and receive feedback
Attendees:
• City of Toronto
• Applicant Team